Performance Indicators of Thua Thien Hue Water Supply & Sewerage Company

1. Customer Indicators

 

Demography

 
Average town / city size 124,290 persons / town
Population density  
in area of responsibility 221 persons/km2
in existing service area N/A
Average Household size 9.6 persons

Connections

 
Service Coverage  
in area of responsibility 37%
in existing service area 37%
Domestic / Non-Domestic  
connections ratio 21.2
consumption rate ratio 3.2
connection charge ratio N/A
New connections  
growth rate 19% / year
domestic connection cost US$ 59.2 /connection
domestic connections 1.3% of per capita GNI
Meter coverage 100.0%
Billed unmetered consumption -7.5%

Water consumption

 
Bulk water exported 0.0% of total metered cons.
Average domestic water charges 1.1% of per capita GNI
Metered consumption rate  
Domestic
80 litres/person/day
Total consumption
105 litres/person/day
  29 m3/connection/month
Total consumption  
metered & unmetered
N/A
  N/A
Share of total metered consumption  
Domestic 76%
Non Domestic 24%
Customer Interactions  
Customer complaints 20.6 / 1000 connections

2. Water Supply Systems O&M

 

System Input

 
Production capacity utilization 56%
Bulk water imported 0% of total system input
System Input Rate 133 litres/person/day
  37 m3/connection/month
System Input ratios  
Input / Distribution ratio 82 m3/day per km pipe
Input / Storage ratio 5 m3/day per m3 storage
Supply Continuity  
customers with continuous supply N/A
time water available 100%

Distribution

 
Distribution / customer 15.0 m. pipe per connection
Storage / customer 0.2 m3 per connection
Residual Chlorine  
sampling compliance N/A
tests passed 98%
Non Revenue Water (Unaccounted for Water)  
Unadjusted figures 21.0% of System Input
  17.1 m3 / km / day
  0.3 m3 / connection / day
adjusted for continuous supply N/A
Unmetered Consumption
 
Unbilled Authorized & Unauthorized Cons. N/A
Unmetered cons. due to meter inaccuracies N/A
Total Unmetered Consumption N/A
Distribution system condition  
Infrastructure Leakage Index [ILI] N/A
Mains failures ratio 2.5 breaks / km pipe / year

3. Human Resource Indicators

 

Human Resource Utilisation

 
Staff ratios  
Overhead staff ratio N/A
Water supply staff ratio 100.0% of total FTE staff
Water related staff  
Total water related staff N/A
Direct water supply staff 10.7 / 1000 connections
  8.8 / 1000 m3/day input
  71.6 / 100 km of pipework

Human Resource Development

 
Staff Training participation rate 0.3 of staff
Staff Training duration rate 10.1 days / staff
Investment in staff training 0.0% of direct labour costs
Investment in staff training 0.0% of total operating costs

Human Resources Costs

 
Average cost of employment per staff N/A
Contracting out / in-house labour ratio N/A

4. Financial Indicators

 

Working ratios

 
Water sales only N/A
Total revenue and expenses N/A

Revenue

 
Total revenue ratio  
Water sales revenue / Total revenue 68.8%
Subsidies & Grants / Total revenue N/A
Revenue Collection period 1.1 months
Unit water price - average
0.14 US$

Expenses

 
Expenses ratio  
Compared to Total Operating expenes  
Overhead expenses 5.7%
Water Operating expenses  
Compared to Water Operating expenses  
Labour costs 24.7%
Electricity costs 9.1%
Chemicals & other materials 2.9%
Contracted out services costs N/A
Other 1021.23390990368
Unit water cost  
Total Cost
N/A
  N/A
Overhead expenses N/A
Labour costs US$ 0.022 / m3 system input
Electricity US$ 0.008 / m3 system input
Chemicals, etc. US$ 0.003 / m3 system input
Contracted out N/A
Other US$ 0.065 / m3 system input
Debt servicing ratio 19.3% of total operating revenue

Fixed Assets

 
Asset Ratios  
Corporate Assets / Total Fixed Assets 10.0%
Water system / Total water related
N/A
Water assets compared to:  
Production capacity US$ 78.12 / m3/day
Distribution size US$ 11.40 / m. pipe
Customers US$ 170.44 / connection

 

Overall Performance (Standardised Indicators)

 

Customer Indicators

Service Coverage in existing service area
-1.5
Meter coverage
0.2
Customer complaints
-0.4

Water Supply Systems O&M

Supply Continuity (time water available)
0.5
Residual Chlorine tests passed
0.5
Unmetered Consumption - total
N/A
Infrastructure Leakage Index [ILI]
N/A

Human Resource Indicators

Total water related staff (cf connections)
N/A
Investment in staff training (cf direct labour costs)
3.0
Average cost of employment (cf per capita GNI)
N/A

Financial Indicators

Working Ratio (water sales only)
N/A
Unit water cost of system input
N/A
Asset Investment rate cf production capacity
-0.1
Debt servicing ratio
N/A
   
Number of Standardized Indicators available
7 /14
Overall Performance Index (OPI)
0.31
Overall Ranking
8/ 47

Back to Benchmarking Home

SEAWUN © 2004-2005 - All rights reserved
Designed by Hung Son @ Perfect-Digital.com